  • Product Update 24.0.04.20409 for Microsoft Dynamics 365 Business Central

New Releases in this Update

Update ID Type Title Functional Area
PE-326 Enhancement

Aged A/P with Retention by Job Report - Enhance formatting & Print to Excel

Reports

PE-329 Enhancement

Revenue Recognition - Excel Import Functionality

Revenue Recognition

PE-339 Enhancement

Limit POC% to 100% Max.

Project Forecast

PE-368 Enhancement

User Task Category - Add to the User Task List Page

Field Management

PE-394 Improvement

Committed Amount Tax Discrepancy

Purchase Order

PE-397 Enhancement

Changes in Version 25 as per Base BC 25

Microsoft Changes

PE-398 Enhancement

Events Required for Project Forecast Sheet - Request from Sudhir's Team

Project Forecast

PE-399 Enhancement

G/L Account UOM on Project Planning Lines via Corrective Credit Memo on Posted SI

ProjectPro Basics

PRJCTPR-414 Enhancement

Rev Rec (JFW)- G/L Entries for Reversal Process

Revenue Recognition

PRJCTPR-416 Hot Fix

Progress Billing - Option 3 with Multiple Retention and No Tax

Progress Billing

PRJCTPR-417 Improvement

Improve Performance for the Revenue Recognition Process (Telemetry)

Revenue Recognition

PRJCTPR-419 Hot Fix

Project Journal Posting Issue - Source Code

ProjectPro Basics

PRJCTPR-422 Enhancement

Revenue Recognition Units Complete POC Calculations

Revenue Recognition

PRJCTPR-423 Hot Fix

Job Daily Log Error in case of Zip Code is not validated by Google

ProjectPro Basics

PRJCTPR-424 Enhancement

Project No. & Project Task No. is not Updating to Purchase Lines from Order Planning

ProjectPro Basics



Release Note Details

PE-326

Enhancement - Aged A/P with Retention by Project Report - Enhance formatting & Print to Excel

The report now has enhanced format with an added filter for Projects. This is also available for an Excel print as well and can be attained by enabling “Print to Excel”.

Release September image 01

PE-339

Enhancement - Limit POC% to 100% Max.

The POC % has been limited to 100% for below columns on their pages/reports:

  • Project Summary Details - Job Percent Complete

  • Revenue Recognition Summary Details - POC%

  • Revenue Recognition Report/Batch - POC%

  • OPS Manager Report - “Current Percent Complete”

Hence, any calculations related to POC% should be calculated with 100% even if the actual calculation is more than 100%. For example: Gross Revenue = POC% * Contract Value

PE-368

Enhancement - User Task Category - Add to the User Task List Page

The “User Task Category” field has now been added to the User Tasks list as well.

Release September image 03

PE-394

Enhancement - Committed Amount Tax Discrepancy.

Committed Amounts now have the same value as those posted to Project Ledger Entries.

PE-399

Enhancement - G/L Account UOM on Project Planning Lines via Corrective Credit Memo on Posted Sales Invoice

Upon posting the sales credit memo for Projects with type G/L Account, the system updates the UOM on the negative Project Planning Lines.

Release September image 04

PRJCTPR-414

Enhancement – Rev Rec (JFW)- G/L Entries for Reversal Process

The entries when posted through Rev Rec, the system now reverses the posted entry if the user tries to post an entry for the same date and against the same job.

PRJCTPR-416

Hot Fix- Progress Billing - Option 3 with Multiple Retention and No Tax.

When a Sales Invoice from Progress Billing is created in case of A/R Retention Method as 3rd and Multiple Retention Boolean as True & Tax Group Code is Non-Taxable, the system now does not give an Inconsistency Error while posting.

PRJCTPR-417

Enhancement - Improve Performance for the Revenue Recognition Process (Telemetry).

Performance is enhanced for the Rev Rec process.

PRJCTPR-419

Hot Fix- Project Journal Posting Issue - Source Code

The error while posting the project journal is now fixed. Additionally, a new projects setup has been introduced for JMP process:

Release September image 05

PRJCTPR-422

Enhancement – Revenue Recognition Units Complete POC Calculations

The Revenue Recognition Report/Batch now considers the POC method “Units Complete”. A new Boolean has been added to the batch to give the option to either include sub-levels or not.

Release September image 05

PRJCTPR-423

Enhancement - Job Daily Log Error in case of Zip Code is not validated by Google

There are some Zip Codes which are not available on Google but are accepted by Local Post like V2B 8S4 (Canada). Now, these Zip Codes are also allowed on the Job Daily Log.

PRJCTPR-424

Enhancement - Project No. & Project Task No. is not Updating to Purchase Lines from Order Planning

The “Project No.” and “Project Task No.” are getting updated on the purchase order lines when created from “Order Planning”.

Release September image 06

Release September image 07